A fire stopping deficiency is any gap, missing seal or wrong product where a pipe, cable, duct or joint passes through a fire separation. The fix is the same each time. Identify the rated assembly, choose a tested firestop system for that exact penetration, install it as the system detail shows, and record it before the drywall goes on. This guide covers the deficiencies that turn up most often, how to inspect for them, how to repair them, and how the BC rules and your CPD obligations fit around the work.
TL;DR
- Firestopping seals openings and joints in fire-resistance-rated walls, floors and ceilings so that flame, smoke and hot gases cannot pass through.
- The most common deficiencies are missing firestop, oversized openings, the wrong product, unsupported penetrants and services added later without restoration.
- In BC, firestops are tested to CAN/ULC-S115 and carry an F or FT rating tied to the assembly’s fire-resistance rating.
- Inspect before concealment and record location, system reference, trade and close-up photos. That record protects you at inspection and in a dispute.
- Licensed residential builders need 20 CPD points a year. Our online courses are approved by BC Housing for CPD credits.
Table of Contents
- What firestopping does and why deficiencies matter
- The deficiencies you will see most often
- Fire separation requirements in Canada and BC
- How to inspect for deficiencies before they are covered
- How to correct and document a deficiency
- Where deficiencies cost you
- Keeping your knowledge current through CPD
- Our courses for builders who need CPD credits
- Our view on firestopping
- FAQ
- Sources
What firestopping does and why deficiencies matter
A fire separation is a wall, floor or ceiling built to resist fire for a stated time, for example 45 minutes or one hour. It only works if it is continuous. A plumbing stack, a bundle of cable or a duct cut through it creates an opening, and firestopping closes that opening again. The City of Calgary’s building guidance explains that firestopping preserves the continuity of the separation and limits the passage of flames, smoke, heat and toxic gases.
One unsealed hole can undo the rating of the whole assembly. In a house with a secondary suite, a duplex or a townhouse row, that assembly separates people who sleep at different hours. The failure is also invisible once finishes go on, which is why deficiencies are found late, at occupancy inspection or during a renovation years afterwards.
The deficiencies you will see most often
The same faults repeat across regions and building types. The list below draws on a firestopping inspection guide for building teams and on RICS research on common defects in existing buildings.
| Deficiency | What it looks like on site | Why it fails |
|---|---|---|
| Missing firestop | A pipe, cable or duct passes through a rated wall or floor with nothing sealing the gap | No barrier to flame or smoke at that point |
| Oversized opening | The hole was cut larger than the tested system allows, often around a pipe collar | The system was tested for a maximum annular space (the gap around the penetrant) |
| Wrong product | General-purpose caulk or spray foam used where a tested system is required | The product was never tested for fire separations |
| Overcrowded cables | Many cables bundled through one opening with no room for the sealant | Seal cannot reach every cable |
| Defective collars or wraps | Collars not fixed to the surface, or wraps fitted to the wrong pipe material | The device cannot close the opening as it burns away |
| Poor backing or support | Missing mineral wool, insufficient sealant depth, unsupported pipes | Seal sags, cracks or falls out |
| Later additions | A trade adds a cable or pipe after inspection and never restores the seal | The tested system no longer matches what is installed |
| Joint gaps | Gaps where a rated wall meets a floor, ceiling or another wall, or sits on a non-rated ceiling | Fire bypasses the rated assembly through the joint |
Research from New Zealand, which is not Canadian code but is useful as evidence of what real alteration sites look like, recorded unsealed cable and pipe penetrations, missing intumescent pads behind flush boxes (pads that swell with heat to close the gap), and penetrations sealed on only one side of a floor or ceiling. It also found gaps on the concealed side of rated walls. That last one matters: a firestop that looks fine from the room you are standing in may be open on the other side.
Why residential work is exposed
Residential jobs involve many small penetrations by many trades. Plumbers run ABS, PVC or PEX, electricians run wiring, and mechanical trades run ducts and vents. Kitchener’s guide to adding a second unit lists the common residential penetrants as steel or copper pipes, combustible plastic pipes and electrical wiring. It notes that larger combustible penetrations may need an approved collar or similar device once the limits of caulk are exceeded. Each trade assumes the previous one dealt with the seal, and the gap is left because nobody was assigned to it.

Fire separation requirements in Canada and BC
Canada has a national model code, the National Building Code (NBC), which provinces adopt or amend. In BC the governing document is the BC Building Code. The 2024 edition applied from March 8, 2024, subject to transition rules for permits already in the system. Confirm with your local authority which edition applies to a permit you hold.
Three ideas carry most of the weight:
- Penetrations must be sealed or tightly fitted. Kitchener’s guide states that a service penetration must be tightly fitted or firestopped to maintain the integrity of the separation. The BC Building Code’s Part 9 provisions follow the same logic: where a fire-rated assembly is pierced, the opening is sealed by a firestop that has been tested to CAN/ULC-S115, with an F rating not less than the required fire-resistance rating, or the penetrating item is steel, copper, concrete or masonry and tightly fitted. This is set out in the BOABC summary of the 2024 Part 9 fire protection provisions.
- The product must be tested for the job. CAN/ULC-S115 is the Canadian test standard for firestop systems. Kitchener’s guide warns that many firestop foams are not tested or approved for fire separations, and says the product must meet that standard and be installed to the manufacturer’s specification.
- Ratings must match the assembly. An F rating measures how long the system stops flame passage. An FT rating adds a limit on temperature rise on the unexposed surface, as the Calgary manual explains. Which rating applies depends on the code provision and the assembly. Under NBC 2020, the 2020 CBHCC seminar on penetrations says continuity where a rated separation meets another separation, floor, ceiling or roof is maintained by an FT-rated firestop tested to CAN/ULC-S115.
The requirements keep moving. Ontario’s 2024 code took effect on January 1, 2025, and Quebec has published its own amended code based on NBC 2020. Both changed their penetration and continuity provisions, according to the Ontario code presentation and the NRC’s Quebec code record. If you work outside BC, read that province’s code, not the national model.
How to inspect for deficiencies before they are covered
Inspecting early is cheaper than opening finished walls. Walk each rated assembly after the trades have roughed in and before insulation and drywall.
- Identify the rated assemblies. Use the drawings and permit documents. Mark rated walls, floors and ceilings on site so every trade can see them.
- Find every penetration and joint. Include pipes, cables, ducts, outlet boxes, recessed fixtures, and the joints at the top, bottom and ends of rated walls.
- Match each one to a tested system. The installation should follow the selected system detail: opening size, annular space, sealant depth, backing, mineral-wool density and compression, collars, wraps and support for the penetrating item.
- Check both sides. Confirm that floor and ceiling penetrations are sealed on every face the system detail requires, and that nothing is open on a concealed side.
- Look at movement and damage. Cracks, gaps and damage from later trades are common. RICS also recommends checking for third-party installer certification and records, and confirming whether the wall or floor is a fire-rated compartment.
- Record what you found. Details follow in the next section.
If a site condition does not match any system detail, do not improvise. Field differences should be reviewed by the design team and qualified firestop technical resources before the opening is closed.
How to correct and document a deficiency
The repair has to restore the rating, not just fill the hole. Use a tested, listed firestop system that fits the actual assembly and penetrant, and install it exactly as that system’s detail describes. Kitchener’s warning about untested foams applies here: a can of general-purpose foam from a hardware store is not a firestop system.
For each deficiency, write down:
- the location, and a reference to the assembly
- the type of penetration or joint
- the observed condition, described neutrally and with measurements
- the firestop system reference you used
- the date, close-up photos, and the trade responsible
- the repair status and reinspection
The inspection guide recommends actionable, neutral descriptions tied to measured conditions, so the trade can repair and reinspect the exact issue without argument about what was meant. A note that says “gaps in basement wall” cannot be closed out. A note that says “75 mm PVC stack through the suite separation, level 1, no collar, 20 mm gap” can.
In BC, builders must also keep their own compliance records. Our guide to professional recordkeeping for BC residential builders sets out a routine that works for firestop photos and sign-offs just as well as for contracts and invoices.
Where deficiencies cost you
An open firestop is a safety issue first. It also becomes a business problem. A failed inspection holds up occupancy, and a wall opened after handover is paid for out of your margin. A missed deficiency can also feed a warranty complaint or an insurance dispute. If you are weighing how a claim would play out, read our overview of construction insurance claims in Canada.
Firestopping sits beside other hidden-work problems. Water entry through the envelope is found the same way, by inspecting before cover-up, and our building envelope inspection guide applies the same discipline to that work. The wider picture of what a BC builder has to cover is in construction business compliance in BC.
Keeping your knowledge current through CPD
Codes change, products change, and trades turn over on your sites. For a licensed residential builder in BC, keeping up is also a licensing condition. BC Housing requires general contractors to complete at least 20 CPD points related to residential construction during each one-year licence term. You earn two points per hour of formal learning and one point per hour of informal learning. Points must be reported through the Licensed Residential Builders portal before you apply to renew. You must keep your CPD records for three years after the licence term ends, because BC Housing may audit them.
Our licensing requirements guide and the page on continuing education for BC residential builders walk through how the points fit into renewal.
Our courses for builders who need CPD credits
Our CPD courses are online self-paced video courses, approved by BC Housing for CPD credits. You work through them when your schedule allows, with no final exams, and you keep lifetime access. Live customer support is available seven days a week. Each course is $29 as a one-time purchase.
Courses that sit close to the issues in this article include Residential Building Science for Contractors, Construction Safety and Risk Management, and Risk Management and Contingency Planning. Construction Contracts and Dispute Resolution Online is relevant when a hidden defect turns into a disagreement over who pays. You can see all ten on our online courses for contractors page.

Our view on firestopping
Most firestop deficiencies we hear builders describe are not skill problems. They are coordination problems. Five trades touch the same wall, each assumes another sealed it, and the drywall goes up before anyone has looked.
The builders who avoid this treat firestopping like any other controlled step in the job. They name who is responsible, they inspect before cover-up, and they keep a photo and a system reference for every penetration. It takes minutes on the day and saves a wall opened later.
That is also why we built our courses around practical, real-world work for BC residential builders. You should be able to take a course in the evening, at your own pace, and use something from it on site the next morning. A $29 course that gives you a better site routine and CPD points toward your renewal is a sensible investment of an hour or two.
Chuck Pulaski
FAQ
What is the most common firestopping deficiency?
Missing firestop is the most common, meaning a pipe, cable or duct passes through a rated assembly with no seal at all. It is closely followed by the wrong product: an untested caulk or foam used where a tested system is required. Both are easy to find if you inspect before the walls are closed in.
Can I use spray foam to seal a penetration in a fire separation?
Only if the product is tested to CAN/ULC-S115 for that assembly and penetrant, and installed to the manufacturer’s specification. Kitchener’s guidance warns that many foams are not tested or approved for fire separations. General-purpose foam does not qualify as a firestop.
What do F and FT ratings mean?
An F rating shows how long a firestop system keeps flames from passing through. An FT rating adds a limit on how much the temperature can rise on the unexposed side, per the Calgary guidance. The rating you need depends on the code provision and the assembly, so check the BC Building Code and your permit drawings.
How many CPD points do I need as a BC residential builder?
You need a minimum of 20 CPD points in each one-year licence term, as set by BC Housing. Formal learning earns two points per hour. Report the points in the Licensed Residential Builders portal before you apply to renew.
Sources
- Fire Stopping Service Penetrations in Buildings, City of Calgary
- 2020 Seminar on penetrations and continuity of fire separations, CBHCC
- Adding a Second Unit in an Existing House, City of Kitchener
- Firestopping Inspection Guide for Building Teams
- SR410 Assessing the risk of non-compliant firestopping, BRANZ
- Why are firestopping defects so common in existing buildings, RICS
- 2024 British Columbia Building Code bulletin, City of Surrey
- BOABC summary of BC Building Code fire protection provisions, Part 9.10
- Building Code Harmonization, 2024 Ontario Building Code Part 3 presentation
- Quebec Construction Code, Chapter I: Building, NRC
- Continuing Professional Development (CPD), BC Housing