A rainscreen is a wall assembly with an outer layer of cladding, an inner water-resistant layer and an air cavity between them. The cavity lets water that gets past the cladding drain out and lets the wall dry. In British Columbia, the building code requires this kind of capillary break on many exposed residential walls. Getting the detail right at windows, roof junctions and the base of the wall matters as much as the cavity itself.
This guide explains the principle, the layers, the code trigger in BC, how fibre cement siding fits in and the details that cause trouble on site. It is written for licensed residential builders who want a clear working picture.
TL;DR
- A rainscreen assumes some water will get behind the cladding and gives it a path to drain and dry, instead of relying on a perfect outer surface.
- The BC Building Code deems a drained and vented air space of at least 9.5 mm behind the cladding to be a capillary break, one of several accepted solutions.
- The code trigger depends on heating degree-days and the moisture index of your location, and exposure can differ by wall face.
- BC Housing field monitoring shows rainscreen walls generally performing well on the coast, but only when penetrations and transitions are detailed so water can leave the wall.
- Our BC Housing approved CPD courses are online self-paced video courses at 29 CAD each.
Table of Contents
- The rainscreen principle in plain terms
- The layers of a rainscreen wall
- What the BC Building Code says
- Why BC treats rainscreens as standard practice
- Rainscreen principle versus pressure-equalized systems
- Does fibre cement siding need a rainscreen?
- Masonry rainscreens
- Where rainscreen installs go wrong
- Why this matters for your licence and your warranty
- Our perspective
- Earn CPD credits on your own schedule
- FAQ
- Sources
The rainscreen principle in plain terms
Wind-driven rain finds gaps. It gets in at joints, fasteners, window edges and cracks in the cladding. A rainscreen accepts that and manages it.
The Rainscreen Association’s technical bulletin defines a rainscreen as an assembly on an exterior wall with at least an outer layer, an inner layer and a cavity between them, sufficient for the passive removal of liquid water and water vapour. The cavity does three jobs:
- It breaks capillary action. Water cannot wick from the back of the cladding into the sheathing membrane, because the two do not touch.
- It drains. Water that penetrates runs down by gravity and leaves at the base through flashing.
- It dries. Air exchange carries off moisture that would otherwise sit in the wall.
The American Wall and Ceiling Industry association describes the air gap as doing two key things: eliminating capillary action between adjacent porous components and equalizing pressure inside the cavity, so wind-driven rain is not pushed through the assembly.
Capillary action, explained
Capillary action is how water moves through tiny gaps or porous material, even upward or sideways, when two surfaces are in close contact. Think of the back of a board pressed against building paper. Water held between them stays wet for a long time. A cavity of even a few millimetres removes that contact.
The layers of a rainscreen wall
From outside to inside, a typical residential rainscreen wall has these parts. The AWCI describes three principal components: an exterior skin that sheds bulk water, a continuous air gap from head to base, and a water-resistive barrier as the second line of defence, with flashing at the base channelling water out of the cavity.
| Layer | What it does | Typical residential detail |
|---|---|---|
| Cladding | First line of defence, sheds most rain | Fibre cement, wood, stucco, panels, vinyl, masonry veneer |
| Drained and vented cavity | Drains, ventilates, breaks capillary contact | Vertical strapping or furring, or drainage material |
| Water-resistive barrier (WRB) | Second plane of protection | Sheathing membrane over sheathing |
| Flashing | Directs water out at the base and over openings | Base flashing with a vented, screened termination |
| Structure and insulation | Carries load and controls heat | Framing, sheathing, insulation |
BC Housing’s illustrated guide to R22+ effective walls describes the standard residential wall in this way: a WRB inboard of the cladding, with a drainage gap between the cladding and the WRB so that water getting past the cladding can drain.
How big should the gap be?
BC Housing’s Builder Insight No. 6 states that a continuous open gap of 10 mm to 19 mm is generally sufficient for residential construction. It is typically made with vertical treated wood strapping or furring, or metal girts. Venting at both top and bottom is the most effective arrangement. Top vents should be protected by flashing or baffles, and soffit terminations should not allow the cavity to ventilate directly into the attic.
The Rainscreen Association explains that very small gaps, about 1/16 to 1/8 inch, often drain adequately but cannot exchange enough air to dry trapped vapour. Moderate gaps of about 1/2 inch allow full drainage and decent airflow. The Pennsylvania Housing Research Center puts the minimum effective gap at 1/4 inch and adds that a true rainscreen has ventilation openings at the top and bottom of the wall to help drying by convection.

For your own work in BC, the code figure below is the number to build to.
What the BC Building Code says
The rule sits in Division B, Section 9.27 of the 2018 BC Building Code (Part 9 covers houses and small buildings). Under 9.27.2.2, a cladding assembly is deemed to have a capillary break where there is a drained and vented air space of at least 9.5 mm behind the cladding over the full height and width of the wall. The same clause lists other accepted solutions:
- an open drainage material at least 9.5 mm thick with at least 80% open cross-sectional area
- hollow-backed metal or vinyl cladding installed horizontally and loosely fastened
- a masonry cavity wall or masonry veneer built to Section 9.20
The code allows the air space to be interrupted by penetrations for windows, doors and services, by flashing, and by nominally vertical furring or strapping, as long as the interruptions do not make up more than 20% of the air space.
When the requirement applies
Under 9.27.2.2(5), exterior walls exposed to precipitation need a first and second plane of protection with a capillary break where:
- heating degree-days are under 3,400 and the moisture index is above 0.90, or
- heating degree-days are 3,400 or more and the moisture index is above 1.00.
Heating degree-days measure how cold a location is over a year. The moisture index combines wetting and drying potential for a location, so wet coastal areas score high. The code includes exceptions, for example for accessory buildings, walls that are not moisture sensitive and mass walls, all in the same section.
Two practical points. First, exposure is not the same everywhere on a lot. The provincial building bulletin on Section 9.27 clarifies that exposure to rivers, lakes, oceanfront or large open fields is not considered normal exposure, and that different faces of a building can have different exposure conditions. Second, local bylaws and the authority having jurisdiction have the final word on your project, so confirm the requirement with the building department before framing is closed in.
BC Housing’s Building Envelope Guide for Houses covers the minimum envelope requirements under Part 9 of the 2018 code, including rainscreens in coastal areas, along with best-practice wall design beyond the minimums.
Why BC treats rainscreens as standard practice
BC Housing’s study of 35 high-rise buildings and 151 wall and window assemblies found that exterior moisture penetration at interfaces and details was the dominant cause of moisture problems. None of the walls incorporating drainage cavities experienced problems, and rainscreen assemblies were identified as required for most buildings in BC’s coastal climate.
Field monitoring on houses points the same way. Builder Insight No. 6 reports six years of monitoring across five buildings in Vancouver’s coastal climate. Rainscreen walls were generally working well, with seasonal moisture in wood and gypsum below safe thresholds. The same document gives useful reference points for sheathing moisture readings:
- Sheathing can rise to about 25% for a few days during sustained 95 to 100% cavity relative humidity.
- Sustained readings of 20 to 30% over more than a month indicate long-term exposure to high humidity.
- Readings above about 28%, the fibre saturation point, most likely indicate a rainwater leak.
If you do envelope inspections, those thresholds help you read a moisture meter with context. Our guide to building envelope inspection for BC builders covers the inspection side.
Rainscreen principle versus pressure-equalized systems
The simplest version, sometimes called an open rainscreen or drained and vented cavity, relies on drainage and ventilation. A pressure-equalized rainscreen adds compartments and vents so that wind pressure on the outside equalizes in the cavity. Wind load then transfers to the air barrier and less water is driven inward.
Architect Tom Oake’s guide notes that equalization always has a time lag, and that pressure equalization does not remove the need for drainage and drying capacity. For Part 9 houses, the drained and vented cavity is the usual approach. Pressure-moderated design is more common on larger, engineered buildings.
Does fibre cement siding need a rainscreen?
This is a common question, and the answer depends on the product, the building and the location.
The National Research Council’s code compliance evaluation for James Hardie products (CCMC 12678-R) requires HardiePanel vertical siding to be installed over wood strapping with a drained and vented air space of at least 10 mm under NBC 2015, or 9.5 mm under NBC 2020, in all areas. For lap siding and shingle products, strapping is required in the wet-climate areas defined by the NBC sentence that matches BC’s 9.27.2.2(5). Elsewhere, the air space created by the board overlap has to stay unobstructed. The evaluation also requires a sheathing membrane, at least 200 mm of ground clearance, corrosion-resistant fasteners and code-compliant flashing.
The manufacturer’s own panel documentation says a minimum 3/8 in (10 mm) capillary break is required on multi-family and commercial projects, and recommends a rainscreen gap as best practice on single-family projects. It also advises against using compressible drainage mats or boards as the capillary break for that product.
Two takeaways for a builder: read the current evaluation and installation sheet for the exact product, and treat the code and local bylaw as the floor. Product sheets say what the maker will accept for warranty. They do not replace the designer’s or builder’s responsibility for water management on the wall as a whole.

Masonry rainscreens
Masonry veneer or a masonry cavity wall built to Section 9.20 is deemed by the BC Building Code to have its own capillary break between the cladding and the backing assembly, as set out in Section 9.27. The same drainage logic applies: the cavity needs a clear path at the base, with flashing and weep openings so water leaves the wall.
Where rainscreen installs go wrong
A correct cavity can still fail at the details. Builder Insight No. 6 stresses that penetrations such as pipes, ducts and hose-bibs, and transitions such as windows, balconies and roofs, must be detailed so water can drain out and dry. It also recommends treated wood for highly exposed walls or open rainscreen designs where water may enter the cavity.
A site checklist to walk before cladding goes on:
- Cavity continuity. Confirm the strapping or drainage layer runs full height without blocking, and that interruptions stay within the 20% limit.
- Base termination. Check that flashing carries water out, and that the vent opening is screened and not blocked by finishes or grade.
- Top venting. Confirm vents are protected by flashing or baffles, and that the cavity does not vent straight into the attic through the soffit.
- Penetrations. Look at every pipe, duct and hose-bib. Water should be able to drain around it, not pool behind it.
- Windows and doors. Confirm the head flashing, sill and jamb sequence with the WRB laps. Our guide on window installation problems walks through the usual failure points.
- Roof-to-wall junctions. Kick-out flashing and step flashing have to deliver water over the cladding face, not behind it. Details on tying roofing into a wall show how roof materials meet the wall plane. Our roof leak prevention guide adds an inspection view.
- Ground clearance. Keep the cladding well above finished grade. For fibre cement, the evaluation above sets at least 200 mm.
Writing these checks into your quote and site documents also helps with disputes later. Construction contracts and dispute resolution is one of the topics in our course list.
Why this matters for your licence and your warranty
Envelope failures are the kind of defect that produces warranty claims and licensing complaints. BC residential builders must meet continuing professional development requirements for licence renewal, and knowing the building science behind a wall assembly is part of working to the standard. Our resources explain BC licensing requirements and new home warranty requirements in more detail.
Our perspective
Most envelope problems we hear builders talk about are not about a missing product. They come from a detail that nobody owned: a hose-bib sealed on the outside with no way for water to leave behind it, or a strapping run that stops at a window head.
A rainscreen is simple to describe and unforgiving to build carelessly. The cavity only works if it is continuous, vented and connected to flashing that actually exits water. That is a habit of mind as much as a code clause, and it is why we build our CPD courses around practical, real-world content for BC residential builders.
Our courses are approved by BC Housing for CPD credits. They are online self-paced video courses with no final exams, so you can study around your site schedule and get live support seven days a week if you have a question. Residential Building Science for Contractors is one of the courses in the catalogue for builders who want to strengthen their grounding in how walls manage moisture.
Chuck Pulaski
Earn CPD credits on your own schedule
If you are renewing your licence this cycle, you can complete your CPD with us online. Each of our ten courses is 29 CAD as a one-off purchase, with lifetime access, no final exams and live customer support seven days a week. They are online self-paced video courses, and our courses are approved by BC Housing for CPD credits.

See the full list on our online CPD courses for contractors page, or read how to complete 20 BC builder CPD points online.
FAQ
What is a rainscreen in simple terms?
A rainscreen is a wall with a gap between the outer cladding and the water-resistant layer behind it. Water that gets past the cladding drains down the gap and out at the base, and air moving in the gap dries the wall. The gap also stops water from wicking between touching surfaces.
How deep does the air gap need to be in BC?
The BC Building Code deems a drained and vented air space of at least 9.5 mm behind the cladding, over the full height and width of the wall, to be a capillary break. BC Housing’s guidance says a continuous gap of 10 mm to 19 mm is generally sufficient for residential construction. Confirm local requirements with your building department.
Do all BC homes need a rainscreen?
Not by one blanket rule. Under 9.27.2.2(5), the requirement depends on heating degree-days and the moisture index for the location, and some wall types or buildings are excepted. Exposure can also differ between faces of the same building, so check the code and your local authority for each project.
Does a masonry veneer need a separate rainscreen?
The code deems a masonry cavity wall or masonry veneer built to Section 9.20 to have a capillary break already. You still need the cavity to drain, with flashing and weep openings at the base and proper detailing at openings.
Does fibre cement siding need a rainscreen?
It depends on the product and the area. The national evaluation for James Hardie products requires strapping and a drained and vented air space for vertical panels in all areas, and for lap and shingle products in the wet-climate areas defined by the code. Read the current installation instructions for your product, and follow the stricter of the code and the manufacturer.
Sources
- RAiNA Technical Bulletin: Defining Rainscreen Wall Performance
- AWCI: Rainscreen Defined
- BC Housing Illustrated Guide: R22+ Effective Walls in Residential Construction
- BC Housing Builder Insight No. 6: Rainscreen Walls
- Pennsylvania Housing Research Center: Rainscreen Gaps in Exterior Walls
- BC Building Code 2018, Division B, Section 9.27 Cladding
- BC Housing Building Envelope Guide for Houses
- BC Housing: Building Envelope Design, Construction Success Factors (high-rise study)
- Tom Oake: The Rain Screen Wall
- NRC CCMC 12678-R evaluation
- HardiePanel Vertical Siding Product Description (Canada)