Good change order management comes down to one habit: no changed work starts until the scope, price and time impact are agreed in writing and signed by both sides. Everything else in this guide supports that habit: how to log a change, price it fully, document it, get it approved and keep a record you can defend later. It is written for licensed residential builders and general contractors in British Columbia.
TL;DR
- A change order is a written agreement, signed by the owner and contractor, that changes the scope, the contract price, the contract time, or all three.
- Log every change the day it appears, price the direct cost, overhead and profit, and the schedule impact, then get a signature before work begins.
- Canadian industry protocols suggest a 21 calendar day turnaround: 7 days for your quotation, 14 days for the owner’s decision.
- On BC Housing-funded work, supplementary general conditions cap markups and add approval steps, so read them before you quote.
- Change orders touch contracts, estimating, scheduling and risk, which are the same topics covered in CPD courses for BC residential builders.
Table of Contents
- What a change order is, and what it is not
- Why change orders need management
- The change order process, step by step
- What a change order should contain
- Pricing a change order and its schedule impact
- Who approves, and when work can start
- BC Housing requirements
- Preventing disputes before they start
- Our perspective
- Build the skills behind your change orders
- FAQ
- Sources
What a change order is, and what it is not
A change order is the final, agreed form of a change. The Ottawa Construction Association’s protocol defines a change order as a written order, agreed by the owner, contractor and consultant, that authorizes changes to the scope of the work, the contract sum and the contract time.
Several other documents sit around it, and mixing them up causes most of the early confusion on site:
| Document | What it does | Does it authorize work? |
|---|---|---|
| Proposed change (or contemplated change notice) | Alerts you to a possible change and invites a quotation | No |
| Change order | Records agreement on scope, price and time | Yes, once signed |
| Change directive | Lets work proceed while the price is still being negotiated | Yes, before price is agreed |
| Supplemental instruction | Clarifies or interprets the contract documents | Only if no price or time change is involved |
These distinctions follow the Ontario Association of Architects’ guidance on supplemental instructions, which notes that if a supplemental instruction involves a change to price or time, a change order or change directive should be issued instead. The RAIC’s contract changes guidance describes the same process: contemplated change notices, change orders and change directives, each tracked in a common format.
If your contract is a standard CCDC form, the Canadian Construction Documents Committee publishes CCDC 16, the 2024 Guide to Changes in the Contract. It explains the key terms, the change process, methods for adjusting the contract price and claims.
Why change orders need management
Change orders are where margin is most often lost. The OCA protocol says cost is the most common area of dispute in the change order process, with recoverable direct cost, overhead and profit percentages, and impact factors causing most impasses. It also notes that many subcontractors believe change orders are not profitable for them, and that changes often hurt the rest of the project’s progress and budget.
In practice, the problems are usually procedural, not technical:
- Work starts on a verbal “go ahead” and the price is argued afterward.
- The quote covers the new material and labour but ignores the effect on the schedule.
- Nobody records why the change happened, so responsibility is unclear.
- Several small changes pile up and their combined effect is never priced.
A consistent process removes each of these.
The change order process, step by step
- Log the change the day it is identified. Record what triggered it (owner request, site condition, design clarification, authority requirement), who raised it, and when. The RAIC recommends keeping a log of all notices, change orders and directives with sequential numbering.
- Give written notice. Check your contract for any notice deadline. Many contracts set one, and a late notice can put your recovery at risk even when the claim is sound.
- Price the change. Include direct costs, overhead and profit, and the schedule effect (see the pricing section below).
- Submit a qualified quotation. State what the price covers and what it does not.
- Negotiate and agree. Both sides must agree on scope, price and time. The American Bar Association’s primer says a valid change order requires agreement on all terms, after which a formal written change order is prepared and signed by all parties. That article is written from a US perspective, but the principle holds under Canadian contract forms too.
- Sign, then start. Do not begin the changed work until the change order is signed, except under a change directive.
- Close out. Update your log, the revised contract value and the revised completion date, and pass any matching changes down to subcontractors.
Realistic timing
The Manitoba Construction Association’s protocol recommends a 21 calendar day turnaround for change orders: you submit a properly prepared quotation within 7 calendar days, and the owner approves or rejects within 14. Your own contract may set different periods, so treat these as a benchmark and follow the contract wording.

What a change order should contain
A vague change order invites a dispute. A law firm presentation on change orders under the Manitoba Heavy Construction Association’s guidance, available from HT Law, says a formal change order should address:
- the change in scope of work
- the change in price, if any
- the change in contract time, if any
- signatures of both owner and contractor, and a date
- a unique number
- the contract being amended
- the contract provision that governs the change
The RAIC adds that, for a change order, the architect should state the initial contract value, the value of changes approved to date, the value of this change and the time added or removed, plus a summary of contract value and time after approval. It also recommends a “reason” line, with short entries such as emergent site condition or change requested by owner. That one line saves a lot of arguing later.
Records worth keeping
Keep a file for each change that lets a third party follow the story without you in the room:
- the trigger: the email, instruction, RFI response or site observation
- dated photos with location notes
- daily reports that name the change
- supplier quotes, subcontractor quotes and invoices
- signed time-and-material tickets, where used
- all notices sent and the replies
- the schedule before and after the change
The point is proof. If the owner questions the cost six months later, a dated record does the arguing for you.
Pricing a change order and its schedule impact
A defensible price has three layers.
Direct cost. Labour, materials, equipment and subcontractor costs the change requires, supported by quotes or time records.
Overhead and profit. The MCAC protocol states that overhead is billed at 10 per cent as a guideline and should not slide up or down with the size of the change. Your contract may fix different percentages, so check it first.
Time and impact. A change can extend the schedule and add supervision, site services and equipment time. The MCAC protocol advises that if you claim impact costs, you should hold a detailed baseline schedule and track actual progress against it. Without a baseline, an impact claim is hard to support.
Qualify your quotation
The same protocol recommends qualifying change quotations: say that the price addresses only what is known at the time, covers only the direct cost of that change, and does not include the cumulative effect of multiple changes or the effect on other scope. State that you reserve the right to request compensation if those costs are incurred. Small wording, large protection.
A worked example
Say an owner asks you to relocate a bathroom wall after framing. Your direct cost, from your own quotes and time records, is made up of reframing labour, new materials and an extra plumbing visit. You add overhead and profit as your contract allows. Then you ask the question many builders skip: does the plumbing rough-in move back two days, and does that push inspection or drywall? If yes, the schedule effect goes into the change order as added days, in writing, before anyone signs. The number is yours to calculate from your own costs, but the structure is always the same: direct cost, markup, time.
If you want a structured way to build these numbers, the course on estimating, bidding and procurement for residential contractors covers the estimating side, and the construction scheduling and timeline management course covers how to show the effect of a change on the schedule.
Who approves, and when work can start
The rule of thumb: the people with authority to bind each side sign, and the work starts after. Under a stipulated price contract, that normally means the owner, the contractor and, where one is engaged, the consultant.
When you cannot wait: change directives
Sometimes a change is urgent. A change directive lets the work proceed while the price is still being negotiated. The MCAC protocol says change orders are the preferred mechanism and that directives should be avoided where possible. It adds that a directive should not reduce the urgency of agreeing a final price. It also suggests that, under a directive and before a price is agreed, contractors should be entitled to invoice progress payments of up to 75 per cent of reimbursable expenses.
A law firm’s guidance on the same topic says that where there truly is no time to negotiate an amendment first, the owner should pay on a cost-plus or time-and-materials basis. If you work this way, record hours, materials and equipment daily and get the foreman’s and owner’s representative’s sign-off on each ticket.
BC Housing requirements

If you work on BC Housing projects, your contract may carry extra rules. BC Housing states that contractors awarded CCDC 2, CCDC 5B or CCDC 14 contracts are subject to its supplementary general conditions, which modify some of the standard CCDC terms.
In its supplementary general conditions for the CCDC 2 stipulated price contract, BC Housing sets the following:
- Adjustments are limited to actual costs plus 15% overhead and profit on the contractor’s own work, 7.5% on the amount for a subcontractor’s work, and 15% on the subcontractor’s actual costs.
- Unless the owner agrees otherwise, increases above $50,000 require competitive pricing and, where reasonably possible, at least three quotations.
- Before the owner approves a change order or change directive, the owner and consultant must notify BC Housing in writing and obtain its prior written approval.
All three points come from the BC Housing supplementary general conditions. Since these documents are updated from time to time, use the version attached to your own contract and ask the consultant if anything is unclear. For private residential work, your contract and your client agreement set the rules instead.
Preventing disputes before they start
Most change order disputes can be traced back to something that was not written down. A few controls help:
- Use standard forms. One template for every change keeps the information consistent.
- Number every change in sequence and keep one log.
- Agree on a process in your contract. State who may authorize changes, how quickly you will quote and how quickly the owner will respond.
- Hold short regular review meetings on open changes so none sits unanswered.
- Explain the reason for each change to the owner in plain language.
- Pass changes down. When a change affects a subcontractor, issue a matching change in writing so your prime and subcontract values stay aligned.
These all depend on knowing your contract. The construction contracts and dispute resolution course and the risk management and contingency planning course are the two most relevant of our courses for this topic. On the money side, the financial management and accounting course helps with tracking the cost of changes against the budget.
Our perspective
Change orders are rarely a problem of bad intentions. They are a problem of habits. A builder who writes up every change the same way, every time, spends less time chasing payment and less time defending the work.
That is why we build our courses around the work you do on a real job: contracts, estimating, scheduling, risk and communication. These are the subjects where change order discipline either exists or does not. Each of our courses is approved by BC Housing for CPD credits, runs fully online at your own pace, and has no final exam, so you can apply an idea on Tuesday’s job and finish the lesson on your own time.
If you take only one thing from this guide, make it this: write it down, price the time as well as the materials, and get the signature before you start.
Jesse
Build the skills behind your change orders
If you are a licensed residential builder renewing your licence, the topics in this guide overlap with several of our CPD courses. Each course costs $29 CAD as a one-time purchase, includes lifetime access, and is approved by BC Housing for CPD credits. Live customer support is available seven days a week.

Browse the full list on our online courses for contractors page and choose the ones that fit the gaps in your own process.
FAQ
What is the difference between a change order and a change directive?
A change order records agreement on scope, price and time before the work happens. A change directive lets work proceed while the price is still being negotiated. Industry protocols prefer change orders and suggest directives be used only when delay would cause real harm.
Can I start extra work before the change order is signed?
The safest practice is no. Start only after both sides have signed, unless a change directive has been issued. If the work is truly urgent, agree in writing to pay on a cost-plus or time-and-materials basis and keep signed daily records.
How long should a change order take to approve?
A widely used Canadian benchmark is 21 calendar days: 7 for the contractor’s quotation and 14 for the owner’s decision. Your own contract may set a different period, so follow its wording and note the dates in your change log.
What overhead and profit can I add to a change order?
It depends on your contract. The MCAC protocol uses 10 per cent overhead as a guideline. On BC Housing projects, the supplementary general conditions set specific caps of 15% and 7.5% depending on whose work it is. Check the version in your contract.
Do BC Housing projects need extra approval for changes?
Under the supplementary general conditions for the CCDC 2 contract, the owner and consultant must notify BC Housing in writing and get its prior written approval before approving a change order or change directive. Ask your consultant how this is handled on your project.
Sources
- Ottawa Construction Association, 2023 Change Order Protocol
- Manitoba Construction Association, Change Order Protocol (2022)
- RAIC CHOP, Contract Changes Management
- Ontario Association of Architects, Supplemental Instructions
- CCDC 16, 2024 Guide to Changes in the Contract
- American Bar Association, Construction 101: The Basics of Change Orders
- HT Law, Change Orders presentation
- BC Housing, Construction Contracts
- BC Housing, Supplementary General Conditions CCDC 2 Stipulated Price Contract